Installation of 110-Ton Large-Scale Equipment for Hydropower Plant

Technology / product information

As part of the Hoa Binh Hydropower Plant expansion project—a key national project with a total investment of over VND 9,200 billion—LILAMA 10 successfully installed a large 110-ton piece of equipment. This achievement highlights the company's technical proficiency and project management capabilities in handling large-scale equipment installation for major hydropower projects.

- Overview
LILAMA 10 is responsible for equipment installation in the Hòa Bình Hydropower Plant expansion project – a nationally significant project in Vietnam with a total investment of over VND 9,200 billion. The project’s objective is to increase power generation capacity and ensure a sustainable electricity supply.
One of the most crucial tasks was the installation of the water turbine runner weighing up to 110 tons. This super-heavy piece of equipment, imported from abroad, is considered a prerequisite for subsequent turbine system installation. Completing this stage with precision and safety not only demonstrates LILAMA 10’s technical expertise but also lays the foundation for installing other equipment such as the turbine cover, turbine shaft, control ring, and turbine guide bearing.

- Key Highlights
Safe and precise installation of a super-heavy 110-ton water turbine runner, an imported component requiring high precision and seamless integration
Comprehensive management of the entire construction process under restricted site conditions at a hydropower plant
Demonstrating LILAMA 10’s execution and project management capabilities for highly complex projects

- Large-Scale Equipment Installation Projects
Ialy Hydropower Expansion: Rotor (400 tons), turbine, stator, and equipment system
Cái Lớn–Cái Bé Irrigation System: Vietnam’s largest sluice gate
National Convention Center: Special steel roof structures
International Projects (Libya, Malaysia, etc.): Fabrication and installation of industrial equipment

Through its ability to precisely install super-heavy hydropower equipment, LILAMA 10 has solidified its position as a leader in meeting the demanding requirements of national-scale projects.

PICKUP

Technology / Product Information

CONTACT

Inquiry

This is the inquiry form for LILAMA 10 Joint Stock Company. Please enter your inquiry.

This service is intended to provide consultation and opinion requests for processing projects.
Please do not use this information for self-promotion or sales activities.
If we receive a complaint from a recipient about the contents of the transmission, we may take measures such as forcibly stopping the use of the service.

Inquiry Type*Required
Message*Required
Attach file

Only image (jpeg, jpg, gif, png, pdf) and compressed file (zip, lzh) extensions are valid. Maximum file size 10MB